More than $250million in major construction contracts have now been awarded for Elizabeth Quay.
The $200million Managing Contractor contract has been awarded to a partnership between Leighton Contractors Pty Ltd and Broad Construction Services Pty Ltd. The contract includes the construction of the 2.7ha inlet, creation of future development sites and new internal roads and the delivery of high quality parks, promenades and an island with a connecting bridge. Inlet construction will commence in mid-2013, starting with excavation on the northern side of Riverside Drive, with the bulk of inlet excavation due for completion in 2014.
To prepare for the construction of the inlet, Georgiou Group is currently undertaking road works and service infrastructure upgrades as part of a $50million forward works contract. Georgiou's contract includes:
Forward works are due for completion in January 2014. Visit our works page for details about the latest works being undertaken on site or subscribe to receive regular updates.
Jetty reconstruction works are being undertaken at Barrack Street Jetty by Maritime Constructions. The works commenced in August 2012 and include the demolition of Jetty 6 (the western jetty), an extension of Jetty 5 and the construction of new finger jetties to Jetty 1 to make way way for construction of the inlet. These works are due for completion in late April 2013.
| Concept Masterplanning and preliminary business case | Complete | |
| Preliminary design, technical investigations and feasibility analysis | Complete |
|
| Statutory approvals and contract procurement | Ongoing | |
| Public works construction and creation of development sites | Ongoing | |
| Progressive marketing and release of private development sites | mid-2012 onwards | |
| Dedicated place management and maintenance | Ongoing |