Yagan Square timelapse 16 January 2017
Category
Works
Date
16 January 2017

Market Hall and Horseshoe Lane construction

Yagan Square building works are underway.

This package of works will see construction of the Market Hall, Horseshoe Lane and other buildings which will house food and beverage operators from late 2017. 

The Market Hall upper concrete slab is completed.

Concrete for the North Bar western stair is scheduled to be poured in the next fortnight.

Work will soon commence on the construction of the water feature and the canopy.