Waterbank surcharging

  • Riverside

Land at the Waterbank site is nearing its final stage of stabilisation – enabling construction to begin later in 2015 – so the sand stockpile has been removed from the corner of the site near Trinity Avenue and Hay Street. Other minor testing and service relocations are now taking place and will be completed in June 2015. There will be some trucks and service vehicles entering and leaving the site off Trinity Avenue, with:

  • Site access limited to 7am and 5pm, Monday to Friday.
  • Road and parking bays remaining open.
  • No work to be undertaken out of hours without approval.

Download the fact sheet or call the MRA Community Information Line on 1800 639 726 for more details about the works.